Topic: GOES-18/19 ABI products delivered to AWIPS, GRB, PDA, SWPC
 
Date/Time Issued: July 20, 2026 1853Z
 
Product or Data Impacted: GOES-18/19 All ABI products and derived products, all scenes delivered to AWIPS, GRB, PDA, SWPC
 
Date/Time of Initial Impact: July 20, 2026 1510Z
 
Date/Time of Expected End: July 20, 2026 1519Z
 
Length of the Outage/Event: 9 Mins
 
Details/Specifics of Change: GCCS experienced a systems degradation during the pre-scheduled Solar Calibration event at 1510UTC, causing loss of a single ABI Full Disk (FD). All services and products are restored at this time. GCCS is currently investigating the root cause of the impact. Further updates will be provided upon change of anomaly status.
 
Contact information for further information: ESPC Operations at ESPCOperations@noaa.gov 301-817-3880 24x7 or goes-r.product.engineering.group@noaa.gov during normal business hours or GCCS Service Desk at gccs.servicedesk@noaa.gov or 844-860-GCCS (4227) 24x7

This notification was sent to ESPC.Notification@noaa.gov mailing list. If you wish to unsubscribe or subscribe to this list, please contact ESPC Help-Desk at ESPCOperations@noaa.gov with your request. Please note: it may take up to two business days to process your request. For any additional information you can reach ESPC at 301-817-3880 (24x7)