Update #6:  Engineers are progressing with GOES-19 recovery efforts, and the following instruments are once again delivering data.

CCOR-1 restored at 1545Z
SUVI restored at 1437Z
SEISS restored at 1503Z
EXIS restored at 1608Z

Engineers are continuing recovery efforts for GOES-19 GLM, and an additional update will be sent out once that final recovery has been completed.

Update #5: Engineers are continuing recovery efforts and additional updates will be sent out as all non-ABI GOES-19 instruments are brought back online. 


Update #4: ABI L1b and L2 data from GOES-19 resumed delivery to AWIPS and PDA at 1710Z. Availability of ABI products on GRB followed at approximately 1900Z.

Update #3: DCS and SAR have returned to service as of 1630Z. Engineers will now work to restore ABI and expect imaging to resume by 1900Z. Image navigation may be slightly degraded for the first hour after imaging starts. The GOES-19 instruments will be restored in the following order:

  • ABI
  • GLM
  • SUVI
  • CCOR-1/EXIS/MAG/SEISS

The recovery process to return all GOES-19 instruments to normal operations is projected to take approximately 8 hours.

Update #2: The GOES-19 Safehold has been resolved and engineers are working to prepare for restart of the onboard instruments. More information on the recovery timeline will be provided when known.

Update #1: Engineers report GOES-19 is in Safehold. They are working to recover the satellite and will share a recovery timeline when available.

Topic: GOES-19 All Products and derived products delivered to AWIPS, GRB, PDA, SWPC

 

Date/Time Issued: July 17, 2026 1619Z

 

Product or Data Impacted: GOES-19 All Products and derived products All Scenes delivered to AWIPS, GRB, PDA, SWPC.

 

Date/Time of Initial Impact: July 15, 2026 2023Z

 

Date/Time of Expected End: TBD

 

Length of the Outage: TBD

 

Details/Specifics: GOES-19 All Products and derived products All Scenes delivered to AWIPS, GRB, PDA, SWPC. Engineers are investigating Suspected Source of Anomaly is the Satellite/Instrument.

 

For Further Information Contact: ESPC Operations at ESPCOperations@noaa.gov or 301-817-3880 24x7 or goes-r.product.engineering.group@noaa.gov during normal business hours.

 

This notification was sent to ESPC.Notification@noaa.gov mailing list. If you wish to unsubscribe or subscribe to this list, please contact ESPC Help-Desk at ESPCOperations@noaa.gov with your request. Please note: it may take up to two business days to process your request. For any additional information you can reach ESPC at 301-817-3880 (24x7).