Update #1: This update is to notify completion of all Maintenance Activities and Restoral of all GCCS GOES-18 and GOES-19 products to AWIPS, GRB, NCCF, SWPC, and PDA.
This update also corrects that the GOES-18 impacts were initially unplanned due to anomalous behavior of the GCCS firewalls, but did occur as previously stated.
A ticket has been opened with the firewall vendor to investigate root cause of the GOES-18 impacts.
It has been noted that during this GCCS Maintenance Activity, there was also an NWAVE event as well as Ground System maintenance which may have been additional factor(s) in the total impact.
The Maintenance Activity impacted the GOES-18 and GOES-19 products between 16:28UTC - 16:53UTC.


Topic: GOES-18, 19 All Products products delivered to AWIPS, GRB, PDA, SWPC
 
Date/Time Issued: Jul 01, 2026 2045Z
 
Product or Data Impacted: See Details 
 
Date/Time of Initial Impact: Jul 01, 2026 1626Z
 
Date/Time of Expected End: Jul 01, 2026 1700Z
 
Length of the Outage/Event: 0 Hrs 34 Mins
 
Details/Specifics: GOES-18, 19 All Products products delivered to AWIPS, GRB, PDA, SWPC. Unexpected impacts due to GCCS maintenance.

Contact Information for Further InformationESPC Operations at ESPCOperations@noaa.gov or 301-817-3880 24x7 or goes-r.product.engineering.group@noaa.gov during normal business hours or GCCS Service Desk at gccs.servicedesk@noaa.gov or 844-860-GCCS (4227) 24x7

This notification was sent to ESPC.Notification@noaa.gov mailing list. If you wish to unsubscribe or subscribe to this list, please contact ESPC Help-Desk at ESPCOperations@noaa.gov with your request. Please note: it may take up to two business days to process your request. For any additional information you can reach ESPC at 301-817-3880 (24x7)