Update #4: Operations finished the S-NPP GPS unit recovery efforts on June 4, 2024. Cal/Val and NOAA PAL teams have confirmed that S-NPP science products have valid GPS results. 


S-NPP Science products will be enabled on PDA OPS at 18:00 UTC on June 4, 2024. Science data after 18:00 UTC June 4, 2024 will meet mission specifications. Direct Broadcast (DB) users can use the equivalent S-NPP science Community Satellite Processing Package (CSPP) LEO products for operations.


Update #3: Engineering commenced S-NPP GPS recovery efforts today, June 3, 2024, with early indications showing improved results. Engineering will revisit data quality analysis with the Cal/Val teams based on results overnight.


Update #2: Due to increased degradation seen in all S-NPP science products, all S-NPP science products will be disabled on PDA OPS at 16:00 UTC on May 30, 2024.


While S-NPP High Rate data (HRD) is enabled, Direct Broadcast (DB) users are advised that this S-NPP science data is not yet cleared for operational use. 


This science data will continue to be available through GRAVITE, CLASS and PDA I&T through which the Cal/Val teams and PALs can perform their full analysis.


The anticipated reset of the S-NPP GPS unit is now expected to be executed no earlier than June 3, 2024.


Update #1: PDA OPS subscription for all S-NPP OMPS Limb Profile (LP) Products including blended LTOAST products will be disabled at 21:00 UTC on May 29th, 2024.


Users are advised that these S-NPP LIMB products have been degraded since May 25th, 2024.


As S-NPP High Rate data (HRD) remains enabled for OMPS LP products, Direct Broadcast (DB) users are advised that this S-NPP OMPS LP science data is not yet cleared for operational use.



Topic: GPS invalid on S-NPP spacecraft 


Date/Time Issued: June 04, 2024 1805Z

 

Product(s) or Data Impacted: All S-NPP VIIRS Data Products

 

Date/Time of Initial Impact: May 25, 2024 2230Z


Date/Time of Expected End Time: June 04, 2024 1800Z


Duration: 9 Days 19 Hours 30 Mins


Details: Starting on May 25 at ~22:30 UTC, the GPS on the S-NPP spacecraft toggled to invalid causing the geolocation of all observed data to be inaccurate and out of the mission specifications. Engineering has started planning the execution of the reset of the GPS unit on the S-NPP spacecraft. The anticipated reset of the GPS unit is expected no earlier than May 29, 2024. All PDA OPS subscriptions for all S-NPP VIIRS science products will be disabled at 17:00 UTC on May 28, 2024. 


As S-NPP High Rate data (HRD) remains enabled for all VIIRS products, Direct Broadcast (DB) users are advised that this S-NPP VIIRS science data is not yet cleared for operational use.


The NOAA-21 and NOAA-20 satellites will continue to provide JPSS VIIRS science data as the primary and secondary satellites, respectively.


Contact Information for Further Information: ESPC Operations at ESPCOperations@noaa.gov at 301-817-3880

 

Web Site(s) for Applicable Information: N/A

This message was sent by ESPC.Notification@noaa.gov. You have been sent this and other notifications because you have opted in to receive it. If for any reason, you wish to unsubscribe, please contact ESPC Help Desk at ESPCOperations@noaa.gov or (301) 817-3880. Please note: it may take up to two business days to process your unsubscribe request.