Topic: GOES-18 antenna handover to cause potential for GRB receiver impacts
Date/Time Issued: March 5, 2024 1825 UTC
Product(s) or Data Impacted: GOES-18 GRB data receipt
Date/Time of Initial Impact: March 6, 2024 1700 UTC
Date/Time of Expected End: March 14, 2024
Length of Outage: 8 days
Details/Specifics of Change: On 6 March 2024 at approximately 1700 UTC, the GOES-18 GRB stream will be handed over to an antenna at CBU that utilizes new SGC (Space to Ground Communications) hardware. Some users may experience difficulties receiving GRB data, similar to the GOES-16 GRB issues observed on 12 October 2023 for users whose receivers are impacted. The impact is caused by a change to the BBFRAME being configured as ACM (Adaptive Coding and Modulation) vs CCM (Continuous Coding and Modulation). GOES-18 GRB will remain in this configuration until 14 March 2024.
Contact Information for Further Information: Please email Steve Superczynski at stephen.superczynski@noaa.gov; for 24x7 support, contact ESPC Operations at ESPCOperations@noaa.gov or 301-817-3880
Web Site(s) for applicable information: N/A
This message was sent by ESPC.Notification@noaa.gov. You have been sent this and other notifications because you have opted in to receive them. If for any reason, you wish to unsubscribe, please contact the ESPC Help Desk at ESPCOperations@noaa.gov or (301) 817-3880. Please note it may take up to two business days to process your unsubscribe request.