Topic: Weekly Operations Schedule - Week 39 Issue 3 (Announcements: Addition of 10035; Update of 10019)
Date/Time Issued: September 26, 2023 1629Z
Product(s) or Data Impacted: See list below.
Date/Time of Initial Impact: September 26, 2023 1509Z
Date/Time of Expected End: See list below.
Details/Specifics of Change: See list below
Message number: |
11022 |
Message creation: |
Tue Sep 26 15:08:49 UTC 2023 |
Type: |
Planned Maintenance |
Ann Nr: |
9204 |
Rev: |
0 |
Start Time: |
2023-01-31 09:39:00.0 |
Satellites: |
Sentinel-3B |
Subsystem: |
SRAL |
Subject: |
instrument-calibration |
Impact: |
data-degraded |
Detail: |
Starting 31/01/2023 09:39:49 S3B will start performing SRAL external calibrations over a transponder site in Leonessa. To conduct this transponder pass, the on-board Digital Elevation Model (DEM) altitude value must be temporarily updated in RAM, and is reverted immediately after the pass. A short outage immediately before and after the pass will be introduced, and data should be considered degraded as per non-nominal acquisition mode, for a total duration of approx.27 seconds over the transponder location (42.61607° N, 13.03780° E) for all relative orbits number (RON) 306 - from cycle 75 (inclusive) onwards. |
Revision History: |
|
Status: |
scheduled |
Issue Time: |
2023-01-25 17:19:20.0 |
Services: |
SRAL Level 1 Products
- S3B |
Type: |
Planned Maintenance |
Ann Nr: |
9205 |
Rev: |
0 |
Start Time: |
2023-02-02 10:28:00.0 |
Satellites: |
Sentinel-3B |
Subsystem: |
SRAL |
Subject: |
instrument-calibration |
Impact: |
data-degraded |
Detail: |
Starting 02/02/2023 10:28:30 S3B will start performing SRAL external calibrations over a corner reflector site in Spain. To conduct this pass, the on-board Digital Elevation Model (DEM) altitude value must be temporarily updated in RAM, and is reverted immediately after the pass. A short outage immediately before and after the pass will be introduced, and data should be considered degraded as per non-nominal acquisition mode, for a total duration of approx.26 seconds over the transponder location (42.052°N, 0.7300° E) for all relative orbits number (RON) 335 - from cycle 75 (inclusive) onwards |
Revision History: |
|
Status: |
scheduled |
Issue Time: |
2023-01-25 17:19:08.0 |
Services: |
SRAL Level 1 Products
- S3B |
Type: |
Planned Maintenance |
Ann Nr: |
9258 |
Rev: |
0 |
Start Time: |
2023-02-14 20:35:00.0 |
Satellites: |
Sentinel-3A |
Subsystem: |
SRAL |
Subject: |
instrument-calibration |
Impact: |
data-degraded |
Detail: |
Starting 14/02/2023 20:35:57 S3A will start performing SRAL external calibrations over a transponder in Leonessa, Italy. To conduct this transponder pass, the on-board Digital Elevation Model (DEM) altitude value must be temporarily updated in RAM, and is reverted immediately after the pass. A short outage immediately before and after the pass will be introduced, and data should be considered degraded as per non-nominal acquisition mode, for a total duration of approx.28 seconds over the transponder location (42.61607° N, 13.03780° E) for all relative orbits number (RON) 270 from cycle 95 (inclusive) onwards |
Revision History: |
|
Status: |
scheduled |
Issue Time: |
2023-02-08 09:22:43.0 |
Services: |
SRAL Level 1 Products
- S3A |
Type: |
Service Enhancement |
Ann Nr: |
9447 |
Rev: |
0 |
Start Time: |
2023-04-12 09:00:00.0 |
Subject: |
service-change |
Detail: |
Data access from the Data Centre is being migrated to the Data Store, for easier and faster access. For full details, see the URL provided below. |
Revision History: |
|
Url: |
|
Issue Time: |
2023-03-29 13:44:49.0 |
Services: |
EUMETSAT Data Centre |
Type: |
Service Enhancement |
Ann Nr: |
9846 |
Rev: |
0 |
Start Time: |
2023-07-25 09:00:00.0 |
Subject: |
general-announcement |
Detail: |
As the public release of the new MTG-I1 data is approaching, with the distribution of pre-operational FCI L1c data currently planned for October 2023, we have released a dedicated web page capturing all users need to know to get ready for accessing and using the data. For full details, see the URL provided below. |
Revision History: |
|
Url: |
https://www.eumetsat.int/getting-ready-data-first-mtg-missions |
Issue Time: |
2023-07-26 14:35:41.0 |
Services: |
Type: |
Planned Maintenance |
Ann Nr: |
9838 |
Rev: |
0 |
Start Time: |
2023-08-09 20:15:00.0 |
End Time: |
2023-09-30 23:00:00.0 |
Satellites: |
MET-9 |
Subject: |
eclipse-season |
Impact: |
risk-of-degradation |
Detail: |
There is a risk of degraded image quality every night from 20:15 to 23:00 in the given time period. |
Revision History: |
|
Status: |
scheduled |
Issue Time: |
2023-07-27 06:46:45.0 |
Services: |
IODC SEVIRI Level 1.5
Image Data |
Type: |
Planned Maintenance |
Ann Nr: |
9839 |
Rev: |
0 |
Start Time: |
2023-08-23 23:15:00.0 |
End Time: |
2023-10-12 02:00:00.0 |
Satellites: |
MET-10 |
Subject: |
eclipse-season |
Impact: |
risk-of-degradation |
Detail: |
There is a risk of degraded image quality every night from 23:15 to 02:00 next day in the given time period. |
Revision History: |
|
Status: |
scheduled |
Issue Time: |
2023-07-27 06:47:05.0 |
Services: |
0° SEVIRI Level 1.5
Image Data |
Type: |
Planned Maintenance |
Ann Nr: |
9940 |
Rev: |
0 |
Start Time: |
2023-08-28 09:00:00.0 |
End Time: |
2024-01-01 00:00:00.0 |
Satellites: |
Metop-C |
Subsystem: |
ASCAT |
Subject: |
general-announcement |
Impact: |
risk-of-interruption |
Detail: |
Calibrations to support transponder test. Short outages of the ASCAT GDS Level 1, soil moisture and global and regional winds products can be expected, during satellite passes over Madrid |
Revision History: |
|
Status: |
scheduled |
Issue Time: |
2023-08-23 14:57:08.0 |
Services: |
ASCAT Soil Moisture -
Metop-C |
Type: |
Planned Maintenance |
Ann Nr: |
9840 |
Rev: |
0 |
Start Time: |
2023-08-28 22:30:00.0 |
End Time: |
2023-10-15 00:00:00.0 |
Satellites: |
MET-11 |
Subject: |
eclipse-season |
Impact: |
risk-of-degradation |
Detail: |
There is a risk of degraded image quality every night from 22:30 to 01:30 next day in the given time period. |
Revision History: |
|
Status: |
scheduled |
Issue Time: |
2023-07-27 14:26:59.0 |
Services: |
RSS Meteosat
Meteorological Products |
Type: |
Planned Maintenance |
Ann Nr: |
9969 |
Rev: |
1 |
Start Time: |
2023-08-31 04:30:00.0 |
End Time: |
2023-10-16 05:30:00.0 |
Satellites: |
GOES-16 |
Subject: |
eclipse-season |
Impact: |
data-interrupted |
Revision History: |
[Original] GOES East Eclipse season. The 04:30 to 05:30 UTC image data may be unavailable, degraded or incomplete. |
Issue Time: |
2023-09-18 11:02:29.0 |
Services: |
GOES Products |
Type: |
Planned Maintenance |
Ann Nr: |
9968 |
Rev: |
1 |
Start Time: |
2023-08-31 08:30:00.0 |
End Time: |
2023-10-16 09:30:00.0 |
Satellites: |
GOES-18 |
Subject: |
eclipse-season |
Impact: |
data-interrupted |
Revision History: |
[Original] GOES West Eclipse season. The 08:30 - 09:30 UTC image data may be unavailable, degraded or incomplete. |
Issue Time: |
2023-09-18 11:03:24.0 |
Services: |
GOES Products |
Type: |
Planned Maintenance |
Ann Nr: |
9944 |
Rev: |
4 |
Start Time: |
2023-09-05 07:00:00.0 |
End Time: |
2023-09-26 17:00:00.0 |
Subject: |
ground-segment-maintenance |
Impact: |
risk-of-interruption |
Detail: |
Updated end time. |
Revision History: |
[Original] Lannion Station Antenna Chains - MEOS Server Upgrades v5.4.5. There may be disruption to the listed EUMETSAT based services during the maintenance period daily between 07:00 and 15:00 UTC. [Rev.1] Updated end time [Rev.2] Updated end time. [Rev.3] Updated end time. |
Status: |
scheduled |
Issue Time: |
2023-09-19 14:18:03.0 |
Services: |
EARS-ATOVS |
Type: |
Service Enhancement |
Ann Nr: |
9779 |
Rev: |
2 |
Start Time: |
2023-09-13 09:00:00.0 |
End Time: |
2023-09-20 09:00:00.0 |
Subject: |
product-change |
Detail: |
The period of parallel distribution of the current and new products ended on 20 September 2023. |
Revision History: |
[Original] The current Sentinel-3 Altimetry product for Africa will be replaced by a new Sentinel-3 land hydrology thematic product at the end of September 2023 (exact date to be announced). To facilitate user transition to the new product, both current and new products will be distributed in parallel for a period of three weeks, from 5 to 26 September 2023. For full details, see the URL provided below. [Rev.1] The period of parallel distribution of the current and new products will now be from 13 to 26 September 2023. |
Url: |
https://www.eumetsat.int/sentinel-3-altimetry-product-africa-be-replaced |
Issue Time: |
2023-09-21 13:07:47.0 |
Services: |
Type: |
Planned Maintenance |
Ann Nr: |
9981 |
Rev: |
0 |
Start Time: |
2023-09-15 08:15:00.0 |
End Time: |
2023-09-28 09:00:00.0 |
Satellites: |
MET-9 |
Subject: |
Sun-colinearity |
Impact: |
risk-of-degradation |
Detail: |
Sun Colinearity. There is a risk of degraded image daily between 08:15 and 09:00 UTC. |
Revision History: |
|
Status: |
scheduled |
Issue Time: |
2023-09-06 14:20:20.0 |
Services: |
IODC SEVIRI Level 1.5
Image Data |
Type: |
Planned Maintenance |
Ann Nr: |
10013 |
Rev: |
1 |
Start Time: |
2023-09-21 07:44:00.0 |
End Time: |
2023-09-21 09:24:00.0 |
Satellites: |
Sentinel-3A |
Subsystem: |
SRAL |
Subject: |
spacecraft-special-operation |
Impact: |
data-unavailable |
Detail: |
Subject updated to 'spacecraft-special-operation', as part of the operation to patch SRAL to apply OLTC v6.3 on-board. For more information refer to UNS 10001. |
Revision History: |
[Original] Service has been resumed. |
Status: |
recovered |
Issue Time: |
2023-09-21 15:13:48.0 |
Services: |
SRAL Level 2 Marine
Products - S3A |
Type: |
Service Enhancement |
Ann Nr: |
9978 |
Rev: |
0 |
Start Time: |
2023-09-21 09:00:00.0 |
End Time: |
2023-09-21 09:00:00.0 |
Subject: |
new-product |
Detail: |
The NRT IASI NH3 product from AC SAF will be available on EUMETCast from 21 September 2023. For full details, see the URL provided below. |
Revision History: |
|
Url: |
https://www.eumetsat.int/ac-saf-nrt-iasi-nh3-product-eumetcast-soon |
Issue Time: |
2023-09-06 10:25:12.0 |
Services: |
AC SAF - Products |
Type: |
Service Enhancement |
Ann Nr: |
10025 |
Rev: |
0 |
Start Time: |
2023-09-21 09:00:00.0 |
End Time: |
2023-09-21 09:00:00.0 |
Subject: |
general-announcement |
Detail: |
The Daily Land Surface Temperature product from LSA SAF is now available on the EUMETSAT Data Store, as collection EO:EUM:DAT:METOP:LSA-002. |
Revision History: |
|
Issue Time: |
2023-09-21 13:03:10.0 |
Services: |
Data Store and Data
Tailor Web Service |
Type: |
Planned Maintenance |
Ann Nr: |
10014 |
Rev: |
0 |
Start Time: |
2023-09-25 01:40:00.0 |
End Time: |
2023-09-30 06:26:00.0 |
Satellites: |
GOES-16 |
Subject: |
instrument-calibration |
Impact: |
risk-of-interruption |
Detail: |
NOAA has planned a SUVI flat field calibrations campaign. During the period of September 25 - 30, 2023 the calibration will be run each day. All SUVI products will experience an outage during the calibration period. All EXIS products will be flagged for off point during the calibration. The outages are listed individually for each day: September 25, 2023 - 0140 UTC to 0317 UTC - 98 minutes; September 26, 2023 - 0545 UTC to 0626 UTC - 41 minutes; September 27, 2023 - 0545 UTC to 0626 UTC - 41 minutes; September 28, 2023 - 0545 UTC to 0626 UTC - 41 minutes; September 29, 2023 - 0545 UTC to 0626 UTC - 41 minutes; September 30, 2023 - 0545 UTC to 0626 UTC - 41 minutes |
Revision History: |
|
Status: |
scheduled |
Issue Time: |
2023-09-20 10:03:02.0 |
Services: |
GOES Products |
Type: |
Planned Maintenance |
Ann Nr: |
10005 |
Rev: |
2 |
Start Time: |
2023-09-25 21:30:00.0 |
End Time: |
2023-09-25 23:30:00.0 |
Subject: |
general-announcement |
Impact: |
risk-of-interruption |
Detail: |
Time updated. |
Revision History: |
[Original] Small signal level variations with the EUMETCast Europe service have been noticed, which could have differing data reception impacts depending upon the location and antenna size of the user reception station. To mitigate any potential issues, maintenance on the satellite and the uplink service with the contractors is planned on 20 September 2023, with the aim of improving signal levels on the EUMETCast Europe service, provided via EUTELSAT 10B. During the maintenance window, some disruption and short outages to EUMETCast services (BAS, HVS-1 and HVS-2), can be expected. [Rev.1] |
Status: |
scheduled |
Issue Time: |
2023-09-18 13:52:53.0 |
Services: |
EUMETCast-Europe |
Type: |
Planned Maintenance |
Ann Nr: |
10017 |
Rev: |
0 |
Start Time: |
2023-09-26 00:00:00.0 |
End Time: |
2023-09-26 23:59:00.0 |
Satellites: |
Metop-B |
Subsystem: |
SEM |
Component: |
MEPED |
Subject: |
instrument-calibration |
Impact: |
data-unavailable |
Detail: |
SEM MEPED in flight calibration. |
Revision History: |
|
Status: |
scheduled |
Issue Time: |
2023-09-20 14:05:52.0 |
Services: |
SEM AHRPT Metop-B |
Type: |
Planned Maintenance |
Ann Nr: |
10018 |
Rev: |
0 |
Start Time: |
2023-09-26 00:00:00.0 |
End Time: |
2023-09-26 23:59:00.0 |
Satellites: |
Metop-C |
Subsystem: |
SEM |
Component: |
MEPED |
Subject: |
instrument-calibration |
Impact: |
data-unavailable |
Detail: |
SEM MEPED in flight calibration. |
Revision History: |
|
Status: |
scheduled |
Issue Time: |
2023-09-20 14:12:18.0 |
Services: |
SEM L0 - Metop-C |
Type: |
Planned Maintenance |
Ann Nr: |
10016 |
Rev: |
0 |
Start Time: |
2023-09-26 07:18:00.0 |
End Time: |
2023-09-28 03:30:00.0 |
Satellites: |
Sentinel-3A |
Subsystem: |
SLSTR |
Subject: |
instrument-calibration |
Impact: |
data-degraded |
Detail: |
IR Channel(s) products will be degraded for the full duration of the activity until both SLSTR Black Bodies [± Y Cavities] return to their nominal in-flight temperatures. |
Revision History: |
|
Status: |
scheduled |
Issue Time: |
2023-09-20 12:29:30.0 |
Services: |
SLSTR Level 1 Products
- S3A |
Type: |
Planned Maintenance |
Ann Nr: |
10020 |
Rev: |
0 |
Start Time: |
2023-09-26 10:00:00.0 |
End Time: |
2023-09-27 18:00:00.0 |
Satellites: |
Metop-B |
Subject: |
ground-segment-maintenance |
Impact: |
data-delayed |
Detail: |
McMurdo Maintenance. The enhanced timeliness achieved for Metop-B data through the Antarctic Data Acquisition (ADA) system may be interrupted. Therefore only nominal Arctic timeliness may be available during the following maintenance periods: on 26-Sep-2023: 10:00-18:00UTC and on 27-Sep-2023: 10:00-18:00UTC |
Revision History: |
|
Status: |
scheduled |
Issue Time: |
2023-09-20 14:19:31.0 |
Services: |
AVHRR Level 1 -
Metop-B |
Type: |
Planned Maintenance |
Ann Nr: |
10021 |
Rev: |
0 |
Start Time: |
2023-09-26 21:56:00.0 |
End Time: |
2023-09-26 21:57:00.0 |
Satellites: |
Jason-3 |
Subject: |
in-plane-manoeuvre |
Impact: |
data-degraded |
Detail: |
Station keeping manoeuvre. The semi-major axis will be increased by 12.3m resulting in radial orbit errors in the OGDRs. OGDR products may be degraded 30 minutes before and up to 2 hours after the manoeuvre. This will affect the sea surface height, but not the wind and wave content in the products. |
Revision History: |
|
Status: |
scheduled |
Issue Time: |
2023-09-20 15:00:47.0 |
Services: |
Jason-3 OGDR |
Type: |
Planned Maintenance |
Ann Nr: |
10023 |
Rev: |
0 |
Start Time: |
2023-09-27 05:33:00.0 |
End Time: |
2023-09-27 08:15:00.0 |
Satellites: |
Sentinel-3A |
Subject: |
in-plane-manoeuvre |
Impact: |
data-degraded |
Detail: |
Reduced data quality should be expected for data sensed during this period. |
Revision History: |
|
Status: |
scheduled |
Issue Time: |
2023-09-21 07:06:54.0 |
Services: |
SLSTR Level 1 Products
- S3A |
Type: |
Planned Maintenance |
Ann Nr: |
10015 |
Rev: |
0 |
Start Time: |
2023-09-27 08:00:00.0 |
End Time: |
2023-09-27 15:00:00.0 |
Subject: |
ground-segment-maintenance |
Impact: |
risk-of-delay |
Detail: |
Data Centre archive maintenance. During this time, catalogue updates and the processing of orders may be delayed. Ordering client may become unavailable during the maintenance. Users are invited to check out the Data Store (https://data.eumetsat.int/) |
Revision History: |
|
Url: |
|
Status: |
scheduled |
Issue Time: |
2023-09-20 12:04:32.0 |
Services: |
EUMETSAT Data Centre |
Type: |
Planned Maintenance |
Ann Nr: |
9990 |
Rev: |
1 |
Start Time: |
2023-09-27 12:44:00.0 |
End Time: |
2023-09-27 12:45:00.0 |
Satellites: |
Metop-C |
Subject: |
out-of-plane-manoeuvre |
Impact: |
data-unavailable |
Detail: |
Details updated. Burn time = 12:44:25 UTC. Burn duration = 868.9 seconds. |
Revision History: |
[Original] Out-of-plane manoeuvre. Some instrument data will be unavailable or degraded during this period.The exact burn time and instrument affected outage will be announced closer to the day of the manoeuvre. Reduced data quality should be expected for data sensed during this period |
Status: |
scheduled |
Issue Time: |
2023-09-20 14:34:40.0 |
Services: |
SEM L0 - Metop-C |
Type: |
Planned Maintenance |
Ann Nr: |
10035 |
Rev: |
0 |
Start Time: |
2023-09-28 08:35:00.0 |
End Time: |
2023-09-28 08:45:00.0 |
Satellites: |
Sentinel-3B |
Subject: |
in-plane-manoeuvre |
Impact: |
data-degraded |
Detail: |
Reduced data quality should be expected for data sensed during this period. |
Revision History: |
|
Status: |
scheduled |
Issue Time: |
2023-09-26 11:25:33.0 |
Services: |
SLSTR Level 2 Marine
Products - S3B |
Type: |
Service Enhancement |
Ann Nr: |
9921 |
Rev: |
0 |
Start Time: |
2023-09-28 12:00:00.0 |
End Time: |
2023-09-28 13:00:00.0 |
Subject: |
general-announcement |
Detail: |
Training Session on how to access the data during the transition from Eumetsat Data Centre to Data Store. For more information please refer to the URL link below. |
Revision History: |
|
Url: |
https://www.eumetsat.int/data-access-services-how-interact-data-access-apis-through-swagger-ui |
Status: |
scheduled |
Issue Time: |
2023-08-17 11:52:58.0 |
Services: |
Type: |
Planned Maintenance |
Ann Nr: |
9982 |
Rev: |
0 |
Start Time: |
2023-09-29 11:30:00.0 |
End Time: |
2023-10-11 12:15:00.0 |
Satellites: |
MET-10 |
Subject: |
Sun-colinearity |
Impact: |
risk-of-degradation |
Detail: |
Sun Colinearity. There is a risk of degraded image daily between 11:30 and 12:15 UTC. |
Revision History: |
|
Status: |
scheduled |
Issue Time: |
2023-09-06 14:20:11.0 |
Services: |
0° SEVIRI Level 1.5
Image Data |
Type: |
Planned Maintenance |
Ann Nr: |
10019 |
Rev: |
1 |
Start Time: |
2023-09-29 18:41:00.0 |
End Time: |
2023-09-29 19:32:00.0 |
Satellites: |
Sentinel-3A |
Subsystem: |
all-instruments |
Subject: |
instrument-special-operation |
Impact: |
data-degraded |
Detail: |
During the OLCI lunar observation the following NRT products are subject to degradation during the times listed: OLCI - 19:26 to 19:32; SLSTR IR Channels 18:41 to 19:32; SLSTR VIS Channels - 19:14 to 19:32. SRAL NRT products are subject to be degraded and gaps can be experienced from sensing times 2023-09-29T18:42 to 2023-08-29T19:13. SRAL STC and NTC production gaps for sensing times 2023-09-29T18:42 to 2023-09-29T19:13 (RON[1-385] 40 to 42) are expected. |
Revision History: |
[Original] The exact times of the degradation will be announced closer to the day of the OLCI lunar calibration. |
Status: |
scheduled |
Issue Time: |
2023-09-25 13:48:06.0 |
Services: |
OLCI Level 2 Marine
Products - S3A |
Type: |
Planned Maintenance |
Ann Nr: |
10032 |
Rev: |
0 |
Start Time: |
2023-09-30 10:50:00.0 |
End Time: |
2023-09-30 11:00:00.0 |
Satellites: |
GOES-16 |
Subject: |
instrument-calibration |
Detail: |
A GOES-16 ABI solar calibration scan is planned on 30 September 2023. Between 11:50 and 10:55 UTC GOES-16 ABI will operate in Continuous Full Disk Mode (mode 4) instead of 10-minute Flex Mode (mode 6). Filenames will change to reflect the mode 4 operations, e.g.: OR_ABI-L1b-RadF-M4C01_G16_s20232731050[SSS]_e20232731055[SSS]_c202327310[mmssSSS]-118900_0.nc. ABI 10-minute Flex Mode (Mode 6) will resume at 11:00 UTC |
Revision History: |
|
Status: |
scheduled |
Issue Time: |
2023-09-25 11:29:15.0 |
Services: |
GOES Products |
Type: |
Service Enhancement |
Ann Nr: |
10033 |
Rev: |
0 |
Start Time: |
2023-10-02 09:00:00.0 |
End Time: |
2023-10-02 09:00:00.0 |
Subject: |
product-change |
Detail: |
The distribution of Met Office ATD lightning data on EUMETCast will be stopped on 2 October 2023. New LEELA lightning data will soon be available on EUMETCast. For more details, see the URL provided below. |
Revision History: |
|
Url: |
https://www.eumetsat.int/lightning-product-met-office-be-replaced |
Issue Time: |
2023-09-25 15:26:26.0 |
Services: |
Type: |
Planned Maintenance |
Ann Nr: |
10031 |
Rev: |
0 |
Start Time: |
2023-10-02 14:50:00.0 |
End Time: |
2023-10-02 15:00:00.0 |
Satellites: |
GOES-18 |
Subject: |
instrument-calibration |
Detail: |
A GOES-18 ABI solar calibration scan is planned on 2 October 2023. Between 14:50 and 14:55 UTC GOES-18 ABI will operate in continuous Full Disk Mode (mode 4) instead of 10-minute Flex Mode (mode 6). Filenames will change to reflect the mode 4 operations, e.g.: OR_ABI-L1b-RadF-M4C01_G18_s20232751450[SSS]_e20232751455[SSS]_c202327514[mmssSSS]-136002_0.nc. ABI 10-minute Flex Mode (Mode 6) will resume at 15:00 UTC. |
Revision History: |
|
Status: |
scheduled |
Issue Time: |
2023-09-25 11:24:29.0 |
Services: |
GOES Products |
Type: |
Planned Maintenance |
Ann Nr: |
9983 |
Rev: |
0 |
Start Time: |
2023-10-03 11:00:00.0 |
End Time: |
2023-10-14 11:45:00.0 |
Satellites: |
MET-11 |
Subject: |
Sun-colinearity |
Impact: |
risk-of-degradation |
Detail: |
Sun Colinearity. There is a risk of degraded image daily between 11:00 and 11:45 UTC. |
Revision History: |
|
Status: |
scheduled |
Issue Time: |
2023-09-06 14:27:29.0 |
Services: |
RSS SEVIRI Level 1.5
Image Data |
Type: |
Planned Maintenance |
Ann Nr: |
10024 |
Rev: |
1 |
Start Time: |
2023-10-04 11:00:00.0 |
End Time: |
2023-10-16 13:00:00.0 |
Subject: |
Sun-colinearity |
Impact: |
data-unavailable |
Detail: |
corrrection of year |
Revision History: |
[Original] Sun interference may affect the EUMETCast broadcast satellites. Users might experience lower signal margin or outages on EUMETCast for several minutes. The exact times and durations of the signal degradation or outages depend on the reception location. |
Status: |
scheduled |
Issue Time: |
2023-09-26 06:04:37.0 |
Services: |
EUMETCast-Europe |
Type: |
Service Enhancement |
Ann Nr: |
9778 |
Rev: |
0 |
Start Time: |
2023-10-12 11:00:00.0 |
End Time: |
2023-11-16 14:00:00.0 |
Subject: |
general-announcement |
Detail: |
A series of sessions to provide training on using the Data Tailor is scheduled between 12 October and 16 November 2023. For full details and to register for the sessions, see the URL provided below. |
Revision History: |
|
Url: |
|
Issue Time: |
2023-07-11 13:41:16.0 |
Services: |
Type: |
Service Enhancement |
Ann Nr: |
10022 |
Rev: |
0 |
Start Time: |
2023-11-30 09:00:00.0 |
End Time: |
2023-11-30 09:00:00.0 |
Subject: |
general-announcement |
Detail: |
Sentinel-6 data will be accessible in EUMETSAT Data Store by the end of November 2023 (exact date to be announced in due course). For more details, see the URL provided below. |
Revision History: |
|
Url: |
https://www.eumetsat.int/availability-sentinel-6-data-data-store |
Issue Time: |
2023-09-20 14:57:57.0 |
Services: |
Name: |
EUMETSAT |
Address: |
Eumetsat-Allee 1 |
Telephone: |
+49 6151 807 3660/3770 |
Fax: |
+49 6151 807 3790 |
E-mail: |
|
Internet: |
Message number: |
11022 |
Message creation: |
Tue Sep 26 15:08:49 UTC 2023 |
Type: |
Planned Maintenance |
Ann Nr: |
9204 |
Rev: |
0 |
Start Time: |
2023-01-31 09:39:00.0 |
Satellites: |
Sentinel-3B |
Subsystem: |
SRAL |
Subject: |
instrument-calibration |
Impact: |
data-degraded |
Detail: |
Starting 31/01/2023 09:39:49 S3B will start performing SRAL external calibrations over a transponder site in Leonessa. To conduct this transponder pass, the on-board Digital Elevation Model (DEM) altitude value must be temporarily updated in RAM, and is reverted immediately after the pass. A short outage immediately before and after the pass will be introduced, and data should be considered degraded as per non-nominal acquisition mode, for a total duration of approx.27 seconds over the transponder location (42.61607° N, 13.03780° E) for all relative orbits number (RON) 306 - from cycle 75 (inclusive) onwards. |
Revision History: |
|
Status: |
scheduled |
Issue Time: |
2023-01-25 17:19:20.0 |
Services: |
SRAL Level 1 Products
- S3B |
Type: |
Planned Maintenance |
Ann Nr: |
9205 |
Rev: |
0 |
Start Time: |
2023-02-02 10:28:00.0 |
Satellites: |
Sentinel-3B |
Subsystem: |
SRAL |
Subject: |
instrument-calibration |
Impact: |
data-degraded |
Detail: |
Starting 02/02/2023 10:28:30 S3B will start performing SRAL external calibrations over a corner reflector site in Spain. To conduct this pass, the on-board Digital Elevation Model (DEM) altitude value must be temporarily updated in RAM, and is reverted immediately after the pass. A short outage immediately before and after the pass will be introduced, and data should be considered degraded as per non-nominal acquisition mode, for a total duration of approx.26 seconds over the transponder location (42.052°N, 0.7300° E) for all relative orbits number (RON) 335 - from cycle 75 (inclusive) onwards |
Revision History: |
|
Status: |
scheduled |
Issue Time: |
2023-01-25 17:19:08.0 |
Services: |
SRAL Level 1 Products
- S3B |
Type: |
Planned Maintenance |
Ann Nr: |
9258 |
Rev: |
0 |
Start Time: |
2023-02-14 20:35:00.0 |
Satellites: |
Sentinel-3A |
Subsystem: |
SRAL |
Subject: |
instrument-calibration |
Impact: |
data-degraded |
Detail: |
Starting 14/02/2023 20:35:57 S3A will start performing SRAL external calibrations over a transponder in Leonessa, Italy. To conduct this transponder pass, the on-board Digital Elevation Model (DEM) altitude value must be temporarily updated in RAM, and is reverted immediately after the pass. A short outage immediately before and after the pass will be introduced, and data should be considered degraded as per non-nominal acquisition mode, for a total duration of approx.28 seconds over the transponder location (42.61607° N, 13.03780° E) for all relative orbits number (RON) 270 from cycle 95 (inclusive) onwards |
Revision History: |
|
Status: |
scheduled |
Issue Time: |
2023-02-08 09:22:43.0 |
Services: |
SRAL Level 1 Products
- S3A |
Type: |
Service Enhancement |
Ann Nr: |
9447 |
Rev: |
0 |
Start Time: |
2023-04-12 09:00:00.0 |
Subject: |
service-change |
Detail: |
Data access from the Data Centre is being migrated to the Data Store, for easier and faster access. For full details, see the URL provided below. |
Revision History: |
|
Url: |
|
Issue Time: |
2023-03-29 13:44:49.0 |
Services: |
EUMETSAT Data Centre |
Type: |
Service Enhancement |
Ann Nr: |
9846 |
Rev: |
0 |
Start Time: |
2023-07-25 09:00:00.0 |
Subject: |
general-announcement |
Detail: |
As the public release of the new MTG-I1 data is approaching, with the distribution of pre-operational FCI L1c data currently planned for October 2023, we have released a dedicated web page capturing all users need to know to get ready for accessing and using the data. For full details, see the URL provided below. |
Revision History: |
|
Url: |
https://www.eumetsat.int/getting-ready-data-first-mtg-missions |
Issue Time: |
2023-07-26 14:35:41.0 |
Services: |
Type: |
Planned Maintenance |
Ann Nr: |
9838 |
Rev: |
0 |
Start Time: |
2023-08-09 20:15:00.0 |
End Time: |
2023-09-30 23:00:00.0 |
Satellites: |
MET-9 |
Subject: |
eclipse-season |
Impact: |
risk-of-degradation |
Detail: |
There is a risk of degraded image quality every night from 20:15 to 23:00 in the given time period. |
Revision History: |
|
Status: |
scheduled |
Issue Time: |
2023-07-27 06:46:45.0 |
Services: |
IODC SEVIRI Level 1.5
Image Data |
Type: |
Planned Maintenance |
Ann Nr: |
9839 |
Rev: |
0 |
Start Time: |
2023-08-23 23:15:00.0 |
End Time: |
2023-10-12 02:00:00.0 |
Satellites: |
MET-10 |
Subject: |
eclipse-season |
Impact: |
risk-of-degradation |
Detail: |
There is a risk of degraded image quality every night from 23:15 to 02:00 next day in the given time period. |
Revision History: |
|
Status: |
scheduled |
Issue Time: |
2023-07-27 06:47:05.0 |
Services: |
0° SEVIRI Level 1.5
Image Data |
Type: |
Planned Maintenance |
Ann Nr: |
9940 |
Rev: |
0 |
Start Time: |
2023-08-28 09:00:00.0 |
End Time: |
2024-01-01 00:00:00.0 |
Satellites: |
Metop-C |
Subsystem: |
ASCAT |
Subject: |
general-announcement |
Impact: |
risk-of-interruption |
Detail: |
Calibrations to support transponder test. Short outages of the ASCAT GDS Level 1, soil moisture and global and regional winds products can be expected, during satellite passes over Madrid |
Revision History: |
|
Status: |
scheduled |
Issue Time: |
2023-08-23 14:57:08.0 |
Services: |
ASCAT Soil Moisture -
Metop-C |
Type: |
Planned Maintenance |
Ann Nr: |
9840 |
Rev: |
0 |
Start Time: |
2023-08-28 22:30:00.0 |
End Time: |
2023-10-15 00:00:00.0 |
Satellites: |
MET-11 |
Subject: |
eclipse-season |
Impact: |
risk-of-degradation |
Detail: |
There is a risk of degraded image quality every night from 22:30 to 01:30 next day in the given time period. |
Revision History: |
|
Status: |
scheduled |
Issue Time: |
2023-07-27 14:26:59.0 |
Services: |
RSS Meteosat
Meteorological Products |
Type: |
Planned Maintenance |
Ann Nr: |
9969 |
Rev: |
1 |
Start Time: |
2023-08-31 04:30:00.0 |
End Time: |
2023-10-16 05:30:00.0 |
Satellites: |
GOES-16 |
Subject: |
eclipse-season |
Impact: |
data-interrupted |
Revision History: |
[Original] GOES East Eclipse season. The 04:30 to 05:30 UTC image data may be unavailable, degraded or incomplete. |
Issue Time: |
2023-09-18 11:02:29.0 |
Services: |
GOES Products |
Type: |
Planned Maintenance |
Ann Nr: |
9968 |
Rev: |
1 |
Start Time: |
2023-08-31 08:30:00.0 |
End Time: |
2023-10-16 09:30:00.0 |
Satellites: |
GOES-18 |
Subject: |
eclipse-season |
Impact: |
data-interrupted |
Revision History: |
[Original] GOES West Eclipse season. The 08:30 - 09:30 UTC image data may be unavailable, degraded or incomplete. |
Issue Time: |
2023-09-18 11:03:24.0 |
Services: |
GOES Products |
Type: |
Planned Maintenance |
Ann Nr: |
9944 |
Rev: |
4 |
Start Time: |
2023-09-05 07:00:00.0 |
End Time: |
2023-09-26 17:00:00.0 |
Subject: |
ground-segment-maintenance |
Impact: |
risk-of-interruption |
Detail: |
Updated end time. |
Revision History: |
[Original] Lannion Station Antenna Chains - MEOS Server Upgrades v5.4.5. There may be disruption to the listed EUMETSAT based services during the maintenance period daily between 07:00 and 15:00 UTC. [Rev.1] Updated end time [Rev.2] Updated end time. [Rev.3] Updated end time. |
Status: |
scheduled |
Issue Time: |
2023-09-19 14:18:03.0 |
Services: |
EARS-ATOVS |
Type: |
Service Enhancement |
Ann Nr: |
9779 |
Rev: |
2 |
Start Time: |
2023-09-13 09:00:00.0 |
End Time: |
2023-09-20 09:00:00.0 |
Subject: |
product-change |
Detail: |
The period of parallel distribution of the current and new products ended on 20 September 2023. |
Revision History: |
[Original] The current Sentinel-3 Altimetry product for Africa will be replaced by a new Sentinel-3 land hydrology thematic product at the end of September 2023 (exact date to be announced). To facilitate user transition to the new product, both current and new products will be distributed in parallel for a period of three weeks, from 5 to 26 September 2023. For full details, see the URL provided below. [Rev.1] The period of parallel distribution of the current and new products will now be from 13 to 26 September 2023. |
Url: |
https://www.eumetsat.int/sentinel-3-altimetry-product-africa-be-replaced |
Issue Time: |
2023-09-21 13:07:47.0 |
Services: |
Type: |
Planned Maintenance |
Ann Nr: |
9981 |
Rev: |
0 |
Start Time: |
2023-09-15 08:15:00.0 |
End Time: |
2023-09-28 09:00:00.0 |
Satellites: |
MET-9 |
Subject: |
Sun-colinearity |
Impact: |
risk-of-degradation |
Detail: |
Sun Colinearity. There is a risk of degraded image daily between 08:15 and 09:00 UTC. |
Revision History: |
|
Status: |
scheduled |
Issue Time: |
2023-09-06 14:20:20.0 |
Services: |
IODC SEVIRI Level 1.5
Image Data |
Type: |
Planned Maintenance |
Ann Nr: |
10013 |
Rev: |
1 |
Start Time: |
2023-09-21 07:44:00.0 |
End Time: |
2023-09-21 09:24:00.0 |
Satellites: |
Sentinel-3A |
Subsystem: |
SRAL |
Subject: |
spacecraft-special-operation |
Impact: |
data-unavailable |
Detail: |
Subject updated to 'spacecraft-special-operation', as part of the operation to patch SRAL to apply OLTC v6.3 on-board. For more information refer to UNS 10001. |
Revision History: |
[Original] Service has been resumed. |
Status: |
recovered |
Issue Time: |
2023-09-21 15:13:48.0 |
Services: |
SRAL Level 2 Marine
Products - S3A |
Type: |
Service Enhancement |
Ann Nr: |
9978 |
Rev: |
0 |
Start Time: |
2023-09-21 09:00:00.0 |
End Time: |
2023-09-21 09:00:00.0 |
Subject: |
new-product |
Detail: |
The NRT IASI NH3 product from AC SAF will be available on EUMETCast from 21 September 2023. For full details, see the URL provided below. |
Revision History: |
|
Url: |
https://www.eumetsat.int/ac-saf-nrt-iasi-nh3-product-eumetcast-soon |
Issue Time: |
2023-09-06 10:25:12.0 |
Services: |
AC SAF - Products |
Type: |
Service Enhancement |
Ann Nr: |
10025 |
Rev: |
0 |
Start Time: |
2023-09-21 09:00:00.0 |
End Time: |
2023-09-21 09:00:00.0 |
Subject: |
general-announcement |
Detail: |
The Daily Land Surface Temperature product from LSA SAF is now available on the EUMETSAT Data Store, as collection EO:EUM:DAT:METOP:LSA-002. |
Revision History: |
|
Issue Time: |
2023-09-21 13:03:10.0 |
Services: |
Data Store and Data
Tailor Web Service |
Type: |
Planned Maintenance |
Ann Nr: |
10014 |
Rev: |
0 |
Start Time: |
2023-09-25 01:40:00.0 |
End Time: |
2023-09-30 06:26:00.0 |
Satellites: |
GOES-16 |
Subject: |
instrument-calibration |
Impact: |
risk-of-interruption |
Detail: |
NOAA has planned a SUVI flat field calibrations campaign. During the period of September 25 - 30, 2023 the calibration will be run each day. All SUVI products will experience an outage during the calibration period. All EXIS products will be flagged for off point during the calibration. The outages are listed individually for each day: September 25, 2023 - 0140 UTC to 0317 UTC - 98 minutes; September 26, 2023 - 0545 UTC to 0626 UTC - 41 minutes; September 27, 2023 - 0545 UTC to 0626 UTC - 41 minutes; September 28, 2023 - 0545 UTC to 0626 UTC - 41 minutes; September 29, 2023 - 0545 UTC to 0626 UTC - 41 minutes; September 30, 2023 - 0545 UTC to 0626 UTC - 41 minutes |
Revision History: |
|
Status: |
scheduled |
Issue Time: |
2023-09-20 10:03:02.0 |
Services: |
GOES Products |
Type: |
Planned Maintenance |
Ann Nr: |
10005 |
Rev: |
2 |
Start Time: |
2023-09-25 21:30:00.0 |
End Time: |
2023-09-25 23:30:00.0 |
Subject: |
general-announcement |
Impact: |
risk-of-interruption |
Detail: |
Time updated. |
Revision History: |
[Original] Small signal level variations with the EUMETCast Europe service have been noticed, which could have differing data reception impacts depending upon the location and antenna size of the user reception station. To mitigate any potential issues, maintenance on the satellite and the uplink service with the contractors is planned on 20 September 2023, with the aim of improving signal levels on the EUMETCast Europe service, provided via EUTELSAT 10B. During the maintenance window, some disruption and short outages to EUMETCast services (BAS, HVS-1 and HVS-2), can be expected. [Rev.1] |
Status: |
scheduled |
Issue Time: |
2023-09-18 13:52:53.0 |
Services: |
EUMETCast-Europe |
Type: |
Planned Maintenance |
Ann Nr: |
10017 |
Rev: |
0 |
Start Time: |
2023-09-26 00:00:00.0 |
End Time: |
2023-09-26 23:59:00.0 |
Satellites: |
Metop-B |
Subsystem: |
SEM |
Component: |
MEPED |
Subject: |
instrument-calibration |
Impact: |
data-unavailable |
Detail: |
SEM MEPED in flight calibration. |
Revision History: |
|
Status: |
scheduled |
Issue Time: |
2023-09-20 14:05:52.0 |
Services: |
SEM AHRPT Metop-B |
Type: |
Planned Maintenance |
Ann Nr: |
10018 |
Rev: |
0 |
Start Time: |
2023-09-26 00:00:00.0 |
End Time: |
2023-09-26 23:59:00.0 |
Satellites: |
Metop-C |
Subsystem: |
SEM |
Component: |
MEPED |
Subject: |
instrument-calibration |
Impact: |
data-unavailable |
Detail: |
SEM MEPED in flight calibration. |
Revision History: |
|
Status: |
scheduled |
Issue Time: |
2023-09-20 14:12:18.0 |
Services: |
SEM L0 - Metop-C |
Type: |
Planned Maintenance |
Ann Nr: |
10016 |
Rev: |
0 |
Start Time: |
2023-09-26 07:18:00.0 |
End Time: |
2023-09-28 03:30:00.0 |
Satellites: |
Sentinel-3A |
Subsystem: |
SLSTR |
Subject: |
instrument-calibration |
Impact: |
data-degraded |
Detail: |
IR Channel(s) products will be degraded for the full duration of the activity until both SLSTR Black Bodies [± Y Cavities] return to their nominal in-flight temperatures. |
Revision History: |
|
Status: |
scheduled |
Issue Time: |
2023-09-20 12:29:30.0 |
Services: |
SLSTR Level 1 Products
- S3A |
Type: |
Planned Maintenance |
Ann Nr: |
10020 |
Rev: |
0 |
Start Time: |
2023-09-26 10:00:00.0 |
End Time: |
2023-09-27 18:00:00.0 |
Satellites: |
Metop-B |
Subject: |
ground-segment-maintenance |
Impact: |
data-delayed |
Detail: |
McMurdo Maintenance. The enhanced timeliness achieved for Metop-B data through the Antarctic Data Acquisition (ADA) system may be interrupted. Therefore only nominal Arctic timeliness may be available during the following maintenance periods: on 26-Sep-2023: 10:00-18:00UTC and on 27-Sep-2023: 10:00-18:00UTC |
Revision History: |
|
Status: |
scheduled |
Issue Time: |
2023-09-20 14:19:31.0 |
Services: |
AVHRR Level 1 -
Metop-B |
Type: |
Planned Maintenance |
Ann Nr: |
10021 |
Rev: |
0 |
Start Time: |
2023-09-26 21:56:00.0 |
End Time: |
2023-09-26 21:57:00.0 |
Satellites: |
Jason-3 |
Subject: |
in-plane-manoeuvre |
Impact: |
data-degraded |
Detail: |
Station keeping manoeuvre. The semi-major axis will be increased by 12.3m resulting in radial orbit errors in the OGDRs. OGDR products may be degraded 30 minutes before and up to 2 hours after the manoeuvre. This will affect the sea surface height, but not the wind and wave content in the products. |
Revision History: |
|
Status: |
scheduled |
Issue Time: |
2023-09-20 15:00:47.0 |
Services: |
Jason-3 OGDR |
Type: |
Planned Maintenance |
Ann Nr: |
10023 |
Rev: |
0 |
Start Time: |
2023-09-27 05:33:00.0 |
End Time: |
2023-09-27 08:15:00.0 |
Satellites: |
Sentinel-3A |
Subject: |
in-plane-manoeuvre |
Impact: |
data-degraded |
Detail: |
Reduced data quality should be expected for data sensed during this period. |
Revision History: |
|
Status: |
scheduled |
Issue Time: |
2023-09-21 07:06:54.0 |
Services: |
SLSTR Level 1 Products
- S3A |
Type: |
Planned Maintenance |
Ann Nr: |
10015 |
Rev: |
0 |
Start Time: |
2023-09-27 08:00:00.0 |
End Time: |
2023-09-27 15:00:00.0 |
Subject: |
ground-segment-maintenance |
Impact: |
risk-of-delay |
Detail: |
Data Centre archive maintenance. During this time, catalogue updates and the processing of orders may be delayed. Ordering client may become unavailable during the maintenance. Users are invited to check out the Data Store (https://data.eumetsat.int/) |
Revision History: |
|
Url: |
|
Status: |
scheduled |
Issue Time: |
2023-09-20 12:04:32.0 |
Services: |
EUMETSAT Data Centre |
Type: |
Planned Maintenance |
Ann Nr: |
9990 |
Rev: |
1 |
Start Time: |
2023-09-27 12:44:00.0 |
End Time: |
2023-09-27 12:45:00.0 |
Satellites: |
Metop-C |
Subject: |
out-of-plane-manoeuvre |
Impact: |
data-unavailable |
Detail: |
Details updated. Burn time = 12:44:25 UTC. Burn duration = 868.9 seconds. |
Revision History: |
[Original] Out-of-plane manoeuvre. Some instrument data will be unavailable or degraded during this period.The exact burn time and instrument affected outage will be announced closer to the day of the manoeuvre. Reduced data quality should be expected for data sensed during this period |
Status: |
scheduled |
Issue Time: |
2023-09-20 14:34:40.0 |
Services: |
SEM L0 - Metop-C |
Type: |
Planned Maintenance |
Ann Nr: |
10035 |
Rev: |
0 |
Start Time: |
2023-09-28 08:35:00.0 |
End Time: |
2023-09-28 08:45:00.0 |
Satellites: |
Sentinel-3B |
Subject: |
in-plane-manoeuvre |
Impact: |
data-degraded |
Detail: |
Reduced data quality should be expected for data sensed during this period. |
Revision History: |
|
Status: |
scheduled |
Issue Time: |
2023-09-26 11:25:33.0 |
Services: |
SLSTR Level 2 Marine
Products - S3B |
Type: |
Service Enhancement |
Ann Nr: |
9921 |
Rev: |
0 |
Start Time: |
2023-09-28 12:00:00.0 |
End Time: |
2023-09-28 13:00:00.0 |
Subject: |
general-announcement |
Detail: |
Training Session on how to access the data during the transition from Eumetsat Data Centre to Data Store. For more information please refer to the URL link below. |
Revision History: |
|
Url: |
https://www.eumetsat.int/data-access-services-how-interact-data-access-apis-through-swagger-ui |
Status: |
scheduled |
Issue Time: |
2023-08-17 11:52:58.0 |
Services: |
Type: |
Planned Maintenance |
Ann Nr: |
9982 |
Rev: |
0 |
Start Time: |
2023-09-29 11:30:00.0 |
End Time: |
2023-10-11 12:15:00.0 |
Satellites: |
MET-10 |
Subject: |
Sun-colinearity |
Impact: |
risk-of-degradation |
Detail: |
Sun Colinearity. There is a risk of degraded image daily between 11:30 and 12:15 UTC. |
Revision History: |
|
Status: |
scheduled |
Issue Time: |
2023-09-06 14:20:11.0 |
Services: |
0° SEVIRI Level 1.5
Image Data |
Type: |
Planned Maintenance |
Ann Nr: |
10019 |
Rev: |
1 |
Start Time: |
2023-09-29 18:41:00.0 |
End Time: |
2023-09-29 19:32:00.0 |
Satellites: |
Sentinel-3A |
Subsystem: |
all-instruments |
Subject: |
instrument-special-operation |
Impact: |
data-degraded |
Detail: |
During the OLCI lunar observation the following NRT products are subject to degradation during the times listed: OLCI - 19:26 to 19:32; SLSTR IR Channels 18:41 to 19:32; SLSTR VIS Channels - 19:14 to 19:32. SRAL NRT products are subject to be degraded and gaps can be experienced from sensing times 2023-09-29T18:42 to 2023-08-29T19:13. SRAL STC and NTC production gaps for sensing times 2023-09-29T18:42 to 2023-09-29T19:13 (RON[1-385] 40 to 42) are expected. |
Revision History: |
[Original] The exact times of the degradation will be announced closer to the day of the OLCI lunar calibration. |
Status: |
scheduled |
Issue Time: |
2023-09-25 13:48:06.0 |
Services: |
OLCI Level 2 Marine
Products - S3A |
Type: |
Planned Maintenance |
Ann Nr: |
10032 |
Rev: |
0 |
Start Time: |
2023-09-30 10:50:00.0 |
End Time: |
2023-09-30 11:00:00.0 |
Satellites: |
GOES-16 |
Subject: |
instrument-calibration |
Detail: |
A GOES-16 ABI solar calibration scan is planned on 30 September 2023. Between 11:50 and 10:55 UTC GOES-16 ABI will operate in Continuous Full Disk Mode (mode 4) instead of 10-minute Flex Mode (mode 6). Filenames will change to reflect the mode 4 operations, e.g.: OR_ABI-L1b-RadF-M4C01_G16_s20232731050[SSS]_e20232731055[SSS]_c202327310[mmssSSS]-118900_0.nc. ABI 10-minute Flex Mode (Mode 6) will resume at 11:00 UTC |
Revision History: |
|
Status: |
scheduled |
Issue Time: |
2023-09-25 11:29:15.0 |
Services: |
GOES Products |
Type: |
Service Enhancement |
Ann Nr: |
10033 |
Rev: |
0 |
Start Time: |
2023-10-02 09:00:00.0 |
End Time: |
2023-10-02 09:00:00.0 |
Subject: |
product-change |
Detail: |
The distribution of Met Office ATD lightning data on EUMETCast will be stopped on 2 October 2023. New LEELA lightning data will soon be available on EUMETCast. For more details, see the URL provided below. |
Revision History: |
|
Url: |
https://www.eumetsat.int/lightning-product-met-office-be-replaced |
Issue Time: |
2023-09-25 15:26:26.0 |
Services: |
Type: |
Planned Maintenance |
Ann Nr: |
10031 |
Rev: |
0 |
Start Time: |
2023-10-02 14:50:00.0 |
End Time: |
2023-10-02 15:00:00.0 |
Satellites: |
GOES-18 |
Subject: |
instrument-calibration |
Detail: |
A GOES-18 ABI solar calibration scan is planned on 2 October 2023. Between 14:50 and 14:55 UTC GOES-18 ABI will operate in continuous Full Disk Mode (mode 4) instead of 10-minute Flex Mode (mode 6). Filenames will change to reflect the mode 4 operations, e.g.: OR_ABI-L1b-RadF-M4C01_G18_s20232751450[SSS]_e20232751455[SSS]_c202327514[mmssSSS]-136002_0.nc. ABI 10-minute Flex Mode (Mode 6) will resume at 15:00 UTC. |
Revision History: |
|
Status: |
scheduled |
Issue Time: |
2023-09-25 11:24:29.0 |
Services: |
GOES Products |
Type: |
Planned Maintenance |
Ann Nr: |
9983 |
Rev: |
0 |
Start Time: |
2023-10-03 11:00:00.0 |
End Time: |
2023-10-14 11:45:00.0 |
Satellites: |
MET-11 |
Subject: |
Sun-colinearity |
Impact: |
risk-of-degradation |
Detail: |
Sun Colinearity. There is a risk of degraded image daily between 11:00 and 11:45 UTC. |
Revision History: |
|
Status: |
scheduled |
Issue Time: |
2023-09-06 14:27:29.0 |
Services: |
RSS SEVIRI Level 1.5
Image Data |
Type: |
Planned Maintenance |
Ann Nr: |
10024 |
Rev: |
1 |
Start Time: |
2023-10-04 11:00:00.0 |
End Time: |
2023-10-16 13:00:00.0 |
Subject: |
Sun-colinearity |
Impact: |
data-unavailable |
Detail: |
corrrection of year |
Revision History: |
[Original] Sun interference may affect the EUMETCast broadcast satellites. Users might experience lower signal margin or outages on EUMETCast for several minutes. The exact times and durations of the signal degradation or outages depend on the reception location. |
Status: |
scheduled |
Issue Time: |
2023-09-26 06:04:37.0 |
Services: |
EUMETCast-Europe |
Type: |
Service Enhancement |
Ann Nr: |
9778 |
Rev: |
0 |
Start Time: |
2023-10-12 11:00:00.0 |
End Time: |
2023-11-16 14:00:00.0 |
Subject: |
general-announcement |
Detail: |
A series of sessions to provide training on using the Data Tailor is scheduled between 12 October and 16 November 2023. For full details and to register for the sessions, see the URL provided below. |
Revision History: |
|
Url: |
|
Issue Time: |
2023-07-11 13:41:16.0 |
Services: |
Type: |
Service Enhancement |
Ann Nr: |
10022 |
Rev: |
0 |
Start Time: |
2023-11-30 09:00:00.0 |
End Time: |
2023-11-30 09:00:00.0 |
Subject: |
general-announcement |
Detail: |
Sentinel-6 data will be accessible in EUMETSAT Data Store by the end of November 2023 (exact date to be announced in due course). For more details, see the URL provided below. |
Revision History: |
|
Url: |
https://www.eumetsat.int/availability-sentinel-6-data-data-store |
Issue Time: |
2023-09-20 14:57:57.0 |
Services: |
Name: |
EUMETSAT |
Address: |
Eumetsat-Allee 1 |
Telephone: |
+49 6151 807 3660/3770 |
Fax: |
+49 6151 807 3790 |
E-mail: |
|
Internet: |
Any email message from EUMETSAT is sent in good faith but shall neither be
binding nor construed as constituting a commitment by EUMETSAT, except where
provided for in a written agreement or contract or if explicitly stated in the
email. Please note that any views or opinions presented in this email are
solely those of the sender and do not necessarily represent those of EUMETSAT.
This message and any attachments are intended for the sole use of the
addressee(s) and may contain confidential and privileged information. Any unauthorised
use, disclosure, dissemination or distribution (in whole or in part) of its
contents is not permitted. If you received this message in error, please notify
the sender and delete it from your system.
This message was sent
by ESPC.Notification@noaa.gov. You have been sent
this and other notifications because you have opted in to receive it. If for
any reason, you wish to unsubscribe, please contact ESPC Help Desk at ESPCOperations@noaa.gov or
(301) 817-3880. Please note: it may take up to two business days to process
your unsubscribe request.