Update #4: The implementation of software build PR.12.06.00 will occur on Monday August 21, 2023, barring a CWD declaration. There are two minor updates that have been made to the initial content which are outlined below:


  1. A minor change has been made in regard to the splitting of the Cloud Fraction Packed (CFP) dataset in the Cloud Cover Layers product. The new 2-dimensional datasets containing the Cloud Fraction (CF) in each of the 5 flight layers will simply be named CF1, CF2,...CF5. 

  2. A metadata update included in this build could potentially cause a full or partial outage for a single image (all scenes) at the time of installation for the following Level 2 products:


Update #3:  The implementation of software build PR.12.06.00 has been delayed and a new target date for installation is not yet set. Once the date of implementation is known, a follow-up notification will be sent.


Update #2:  The implementation of software build PR.12.06.00 has been delayed and will now occur no sooner than Monday July 24, 2023


Update #1: The content for this software build has been updated to include two changes to the Cloud Cover Layers algorithm that were originally part of the PR.12.04.00 software build. Due to this change in content, the release number is also being changed to PR.12.06.00 in order to reflect the additional and more substantial software changes. Below is a summary of the new changes that will be included in PR.12.06.00:



Topic:  GOES-16 and GOES-18 software build (PR.12.06.00) Implementation


Date/Time Issued: August 18, 2023 1601 UTC

 

Product(s) or Data Impacted: GOES-16 & GOES-18 ABI L2+ products

 

Date/Time of Initial Impact: August 21, 2023

 

Date/Time of Expected End: N/A

 

Length of Outage:  N/A

 

Details/Specifics of Change: On or about July 17, 2023, the PR.12.05.01 software build will be placed into Data Operations for both GOES-16 and GOES-18. This build contains metadata updates for  ABI L2+ products. 


For the ABI L2 products, a change is needed to the naming convention of the “L2_processing_param_version” in order to conform to the Product Distribution (PD) requirements. This variable contains the name of the processing parameter files that will be provided to PDA. The following is an example of the change that will be made to the name of the processing parameter container file:


Old name: OR-PARM-LST_v02r00.zip

New name: OR_ABI-L2-PARM-LST_v02r00.zip


Contact Information for Further Information: Please email Steve Superczynski at stephen.superczynski@noaa.gov; ESPC Operations at ESPCOperations@noaa.gov or 301-817-3880  24x7

 

Web Site(s) for applicable information: N/A

 

This message was sent by ESPC.Notification@noaa.gov. You have been sent this and other notifications because you have opted in to receive it. If for any reason, you wish to unsubscribe, please contact ESPC Help Desk at ESPCOperations@noaa.gov or (301) 817-3880. Please note it may take up to two business days to process your unsubscribe request