Update#2: This is a reminder that the GOES-18 Interleaving Test will occur on June 14, 2022 from 1600-2000 UTC
Update #1: The date for the GOES-18 interleave test has changed from June 15th to June 14th
Topic: GOES-18 Interleaving Test June 14, 2022
Date/Time Issued: June 8, 2022 1348 UTC
Product(s) or Data Impacted: GOES-17 (GOES-West) ABI, GLM, Space Weather
Date/Time of Initial Impact: June 14, 2022 1600 UTC
Date/Time of Expected End: June 14, 2022 2000 UTC
Length of Outage: 4 hours
Details/Specifics of Change:
On June 14, 2022 at 1600 UTC, a four hour test of the interleave configuration will be performed on the GOES-17 (GOES-West). This test is a user readiness opportunity to prepare for the operational interleave configurations that will be in place 24 hours per day during the two periods of August 1 - September 6 and October 15 - November 11, 2022.
At the time of the interleave test, GOES-18 will be located in a near-West orbital slot (136.8 degrees West), just 0.4 degrees from GOES-17 (at 137.2 degrees West).
The interleave configuration entails populating the operational GOES-17 GRB (GOES Rebroadcast) service with an “interleave” of GOES-18 ABI data (replacing the GOES-17 ABI data) and GOES-17 GLM and space weather data. See this table for the key to GRB Spacecraft IDs and Metadata: https://www.ospo.noaa.gov/Operations/GOES/documents/GRB%20Interleave%20Spacecraft%20ID's%20and%20Metadata.pdf
In order to ensure continuity of GOES-West ABI operations, GRB users are advised to ensure their end-processing will accept a different ABI platform ID (G18 rather than G17) and instrument ID (FM3 rather than FM2). More information on global attributes is available in the Product User’s Guide (PUG) Volume 4 for GRB: https://www.goes-r.gov/users/docs/PUG-GRB-vol4.pdf
Here is the GOES-West data content of each product distribution service during interleave:
GRB: (netCDF file orbital slot will be "GOES West")
- G18 ABI L1b
- G17 GLM L2+
- G17 Space Wx L1b
PDA: ("GOES West" for products below)
- G18 ABI L1b, CMI (no L2+)
- G17 ABI L1b, CMI, L2+
- G17 GLM L1b, L2+
- G17 Space Wx L1b
- Note PDA cal/val subscriptions have additional G18 data access
CLASS:
- G17 ABI L1b, CMI, L2+
- G17 GLM L1b, L2+
- G17 Space Wx L1b
- Note CLASS cal/val subscriptions have additional G18 data access
NODD (formerly BDP):
- G18 ABI Rad, CMI
- G17 ABI Rad, CMI, L2+
- G17 GLM L2+
- G17 Space Wx L1b
HRIT/EMWIN:
- G18 ABI CMI
- G17 ABI L2+
GNC-A:
- G18 ABI CMI
AWIPS:
- G18 ABI SCMI
- G17 GLM L2+
During the June 14th test, GOES-18 ABI data will still be at a “Beta” level of maturity, minimally validated, and may contain significant errors. Nonetheless, GOES-18 ABI data obtained during this test will be advised for operational use, and may be shared without restriction.
During the Aug-Sep and Oct-Nov interleave periods, GOES-18 ABI data will be at “Provisional” level of maturity, fit for operational use and may be shared without restriction.
This test is subject to delay in the event of a Critical Weather Day declaration.
Note regarding GOES-17 ABI during interleave: GOES-17 ABI will be operating continuously until the GOES-West transition from GOES-17 to GOES-18 in January, 2023. Continuous GOES-17 ABI operations will include the June 14th interleave test and the Aug-Sep and Oct-Nov interleave periods when GOES-17 ABI will have multiple focal plane module temperature (FPM) mitigations including the cooling timeline and multiple FPM set points adjustments.
Contact Information for Further Information: SPSD.UserServices.noaa.gov
Websites for Applicable Information:
https://www.ospo.noaa.gov/Operations/GOES/transition.html
This message was sent to ESPC.Notification@noaa.gov. You have been sent this and other notifications because you have opted in to receive it. If for any reason, you wish to unsubscribe, please contact ESPC Help Desk at ESPCOperations@noaa.gov or (301) 817-3880. Please note: it may take up to two business days to process your unsubscribe request.