Update #1: Products resumed nominal production and delivery at 1422Z
Topic: GOES-16 EUVS Flux
products delivered to GRB, PDA
Date/Time Issued: October 26, 2021 1455Z
Product or Data Impacted: GOES-16 EUVS Flux
products delivered to GRB, PDA.
Date/Time of Initial Impact: October 26, 2021 1241Z
Date/Time of Expected End: October 26, 2021 1422Z
Length of the Outage/Event: 1 hour and 41 Mins
Details/Specifics of Change: GOES-16 EUVS Flux
products delivered to GRB, PDA. Outage due to an anomaly.