Topic: Update #1 GOES-16 (EAST) Geostationary Lightning Mapper Test
Date/Time Issued: February 12, 2021 2014Z
Product(s) or Data Impacted: GOES-16 GLM
Date/Time of Initial Impact: February 17, 2021 0515UTC
Date/Time of Expected End: February 19, 2021 1830UTC
Length of Outage: Multiple 1hr15min outages, one 24 hour degraded product period. See Details below.
Details/Specifics of Change: Starting on Wednesday February 17 at 0515UTC, GOES-16 GLM will perform testing to improve the data product. The outages and degradation period are listed below:
 
      February 17 0515-0630UTC: 1hr15min GLM outage
      February 17 1715-1830UTC: 1hr15min GLM outage
      February 18 0515-0630UTC: 1hr15min GLM outage
      February 18 1715-1830UTC: 1hr15min GLM outage
      February 18 1830 to February 19 1830UTC: 24 hour GLM degraded radiometric data
 
This testing will be postponed in the event of a critical weather day. Events will slip one business day, remaining at the same time of day, until they do not conflict with critical weather day.

Contact Information for Further  Information: ESPC Operations at ESPCOperations@noaa.gov and 301-817-3880.    
 
Web Site(s) for applicable information: N/A
 
This message was sent by ESPC.Notification@noaa.gov. You have been sent this and other notifications because you have opted in to receive it. If for any reason, you wish to unsubscribe, please contact ESPC Help Desk at ESPCOperations@noaa.gov or (301) 817-3880. Please note: it may take up to two business days to process your unsubscribe request.